JAKARTA AND WEST JAVA SUBSTATIONS AND TRANSMISSION LINES

Project Credit Export Stage-1 (1994-1997)

Project value USD 397,275,000

Owner PT. PLN (Persero)

Scope E-P-C

Contruction of Power Transmission System at West Java and Jakarta, Including 500kV  & 150kV Gas Insulated Switchgear, 500 kV & 150 kV  Conventional Substation, 150kV Under Ground Cable, 500 kV & 150kV Overhead Transmission Line and Telecomunication Equipment



POWER TRANSMISSION IMPROVEMENT SECTOR

Power Transmission Improvement Sector Project : ADB LOAN No. 1983-INO East and South Kalimantan Interconnetion : Package C-2 : 150 kV Substations Barikin and Tanjung (2005-2007)

Project value USD 2,599,049

Owner PT. PLN (Persero)

Scope E-P-C

Engineering, Procurement and Construction of 150kV Substation Barikin Tanjung